In Fréjus-Plage, the construction of the Maison des associations began in late May 2026. Earthworks and foundations are 85% complete. The rainwater retention basin infrastructure is finished, and the elevation of the crawl space is ongoing. A crane, installed on September 3rd, will assist with upcoming lifting operations. The placement of the first stones is expected soon. The future two-level building, constructed with solid stone, will span 887 m² and include a large divisible meeting room, a gym, several activity rooms, and a computer room. Delivery is anticipated by the end of June 2027.
The extension of the Aubanel kindergarten, which started in late May 2026, is entering a new phase. Earthworks, foundations, the retention basin, the crawl space, and its upper floor are completed, along with an opening made into the existing school wall. The concrete walls of the ground floor are currently being erected, with 80% progress. The two-level, 462 m² extension will house four classrooms, a dormitory, a library-documentation center, and spaces for the educational team. The project is on schedule, with delivery expected in early April 2027.
In Tour de Mare, the extension work for the Maison des associations, begun in mid-June 2026, has reached a first milestone with the completion of mass earthworks. Foundation earthworks are 50% complete. The installation of the rainwater retention basin is also ongoing. A crane, installed on September 2nd, will remain on site until January or February 2027 to support various construction phases. The future extension of nearly 600 m² will feature a large divisible multi-activity room, three activity rooms, a computer room, restrooms, and a storage area. Construction is proceeding with the existing building remaining open and associative activities continuing. Delivery is planned for the end of June 2027.
These three projects are progressing according to their respective schedules. Deliveries for Fréjus-Plage and Tour de Mare are slated for the end of June 2027, while the Aubanel extension is expected to be delivered in early April 2027.