Launched on July 20, 2026, this project aimed to improve traffic flow and user safety, while integrating environmental considerations into the road's development.
The construction site included several key improvements: better management of rainwater, creation of unsealed parking spaces to reduce soil impermeabilization, development of green spaces, and burying of overhead utility lines for improved visual appeal.
Through this operation, the CoVe continues its efforts to enhance and modernize the territory's economic infrastructure, thereby strengthening the attractiveness of business parks.
The total investment for these works amounts to €393,206.40 including tax. Costs are divided as follows: €363,650.40 for roadworks (Colas), €16,476.00 for lighting (SPIE), and €13,080.00 for green spaces (Bouix). The CoVe also contributed to landscaping by providing mulch from its composting facility in Loriol-du-Comtat.