The filling of the pools, with respective capacities of 70 m³ and 60 m³, takes three hours. This phase is accompanied by water tightness tests and verification of plumbing, filtration, and disinfection networks, ensuring water quality before welcoming visitors.
These improvements, costing 6 million euros excluding tax, are led by Provence Alpes Agglomeration with support from the State, the Sud Region, and the Alpes-de-Haute-Provence Department. Finishing works in the halls and the installation of technical equipment are nearly 90% complete.
Final interventions will focus on adjusting technical installations and finishing touches, with overall completion expected by mid-January 2027. The project handover is scheduled for early February 2027, allowing the spa season to open on 8 March 2027.