For the first time, the ITER assembly team inserted a tokamak sector module between two others already installed in the pit. The operation, which took place on Thursday 26 November, required extreme precision to guide a load of nearly 1,400 tonnes with less than 5 centimetres of clearance on either side at the tightest points. Seven of the nine modules are now in place.
This 24-hour manoeuvre mobilised more than 100 team members across three shifts. The module, standing more than 16 metres tall, was lowered with a radial offset of 140 millimetres to create sufficient space. Despite this manoeuvre, lateral clearances were only 48 millimetres at the tightest points, and the module's outer edge was within 62 millimetres of the nearest piping inside the cryostat wall.
“"I’m very proud of everyone who got us to this point. It was a technically challenging operation that keeps us ahead of the Baseline 2024 schedule and gives us confidence we will have all the tokamak sector modules installed by early spring 2027."
Assembly engineer Josep Pallisa, responsible for the technical aspects, explained that the team had to stop regularly to dampen the module's oscillations, which could reach 15 millimetres. Once in place, the specialised TIPI tools will resolve the radial displacement with a minimum tolerance of 500 microns. Principal construction manager Mathieu Demeyere praised the coordination required to complete this crucial step.