This operation, which took place last September, marks a significant step in the department's services taking charge of such works. Previously, annual repairs were necessary to address the damage caused by this recurring landslide.
The project required the mobilization of 18,000 m3 of rocky material resulting from summer weather events. After crushing, nearly 10,000 m3 of usable fill material were obtained. These materials were transported to the Col Agnel site over three weeks.
The earthworks, measuring 50m long, 6.5m wide, and 3m deep, were completed in 15 days by the teams of the Queyras Technical Center, with support from their colleagues in Savines-le-Lac. The road was rebuilt with "reinforced fill", secured by netting and metal reinforcements.
The total cost of the operation was €40,000, a substantial saving compared to estimates from an external contractor, which would have been around €150,000. This success is also attributed to an exceptional weather window that allowed the teams to focus on this extraordinary project.
The final touch, the wearing course, will be applied next spring, after the winter, to allow for complete material stabilization. This sustainable solution puts an end to annual repairs, offering greater durability to the road.