The hamlet of Camp du Castellet has been the site of major works since the end of September 2026. These operations aim to extend the drinking water network and the wastewater sanitation network, and include the creation of a pumping station.
These interventions are part of a Partnership Urban Project (PUP) and support the development of the hamlet. The construction site began on September 23, 2026, with a provisional duration of four months, ending in late January 2027.
The total cost of the operation amounts to €940,000 including tax.
The main stakeholders in this project are the Project Owner, the Agglomération Sud Sainte Baume, the Project Management entrusted to ENVEO, and the companies EHTP, NGE Routes, SADE CGTH, and Compagnie des Eaux et de l’Ozone.