These works aim to guarantee the longevity of the structure and to ensure safe access conditions for all users of the port. In order to limit the impact on circulation during the construction period, a temporary footbridge has been installed. It allows pedestrians to continue accessing the jetty while ensuring their safety during the operations.
The works, with a total cost of €82,350.41, have an estimated duration of one month. They will continue until 4 December 2026, subject to technical or weather-related delays. With this operation, the TPM Metropolis is continuing its policy of modernisation and maintenance of port facilities, essential for maintaining safe infrastructure adapted to users' needs.